Salient Features of Project
Particulars |
Details/Status |
Project Name |
Four Laning of NH-71 from Madanapalle (Design Km 0.000/Existing Km 0.000 of NH-71) to Pileru (Design Km 55.900/Existing Km 59.250 of NH-71) (Design Length = 55.900 Km) on HAM Mode in the State of Andhra Pradesh |
NH No. (New/old) |
NH-71 |
Scheme/Phase |
Bharatmala Pariyojna |
Mode of Execution |
HAM |
No. of Lanes/Configuration |
Four Lane |
Bid Project Cost |
1577 Cr. |
No. Of Bypasses (Name of Town, Length) |
03 Nos. (1. Chinnatippa-Samudram-vayalapadu-Chintaparthi 21.536 km, 2. Kalikiri 5.490 km, 3. Pileru 7.970 km )
|
No. Of Minor Bridges |
12 Nos. |
No. of Culverts |
134 Nos. |
No. of Flyovers |
09 Nos. |
No. of Major Bridges |
19 Nos. |
No. of ROB |
01 Nos. |
No. of Underpasses |
VUP – 05 Nos., LVUP – 10 Nos. |
Toll Plaza |
01 Nos. |
Concessionaire Name |
G R Madanapalli Pileru Highway Private Limited |
Date of Letter of award(LOA) |
30.03.2022 |
Agreement Date |
02.06.2022 |
Appointed Date |
Awaited |
Construction Period (in Days) |
730 Days |
Schedule Completion Date |
730 days from Appointed Date |
Operation & Maintenance Period |
15 Years from the Commercial Operation Date |
Independent Engineer |
|
Authority Name |
National Highways Authority of India, PIU-Tirupati |
Independent Engineer Mobilization Date |
|